[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898045":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},898045,582,1,"单选题","(2013年)招标控制价综合单价的组价包括如下工作：①根据政策规定或造价信息确定工料机单价；②根据工程所在地的定额规定计算工程量；③将定额项目的合价除以清单项目的工程量；④根据费率和利率计算出组价定额项目的合价，则正确的工作顺序是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","①④②③",false,{"key":16,"text":17,"correct":14},"B","①③②④",{"key":19,"text":20,"correct":14},"C","②①③④",{"key":22,"text":23,"correct":24},"D","②①④③",true,"综合单价的组价：①首先，确定所组价的定额项目名称，并计算出相应的工程量；②其次，依据工程造价政策规定或工程造价信息确定其人工、材料、机械台班单价；③在考虑风险因素确定管理费率和利润率的基础上，计算定额项目合价；④计算工程量清单综合单价，未计价材料费（包括暂估单价的材料费）应计入综合单价。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]