[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898044":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},898044,582,1,"单选题","(2013年)关于招标控制价，下列说法中正确的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","招标人不得拒绝高于招标控制价的投标报价",false,{"key":16,"text":17,"correct":14},"B","利润可按建筑施工企业平均利润率计算",{"key":19,"text":20,"correct":14},"C","招标控制价超过批准概算10%时，应报原概算审批部门审核",{"key":22,"text":23,"correct":24},"D","经复查的招标控制价与原招标控制价误差＞±3%的应责成招标人改正",true,"选项A错，投标人的投标报价高于招标控制价的，其投标应予以拒绝；选项B错，若招标控制价大大高于市场平均价，中标后利润很丰厚，若公布的招标控制价远远低于市场平均价，此限额投标将无利可图；选项C错，招标控制价超过批准的概算时，招标人应将其报原概算审批部门审核。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]