[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898030":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},898030,582,1,"单选题","(2013年)关于招标文件的澄清，下列说法中错误的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","投标人应以信函、电报等可以有形地表现所载内容的形式向招标人提出疑问",false,{"key":16,"text":17,"correct":18},"B","招标文件的澄清应发给所有投标人并指明澄清问题的来源",true,{"key":20,"text":21,"correct":14},"C","澄清发出的时间距投标截止日不足15天的应推迟投标截止时间",{"key":23,"text":24,"correct":14},"D","投标人收到澄清的确认时间可以是相对时间，也可以是绝对时间","招标文件的澄清与修改将在规定的投标截止时间15天前以书面形式发给所有购买招标文件的投标人，澄清时不指明问题的来源。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]