[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898025":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},898025,582,1,"单选题","（2019年真题）采用实物量法与工料单价法编制预算，其工作步骤的差异体现在（）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程量的计算",false,{"key":16,"text":17,"correct":18},"B","直接费的计算",true,{"key":20,"text":21,"correct":14},"C","企业管理费的计算",{"key":23,"text":24,"correct":14},"D","税金的计算","P169-181 实物量法与工料单价法首尾部分的步骤基本相同，所不同的主要是中间两个步骤，即;①采用实物量法计算工程量后，套用相应人工、材料、施工机具台班预算定额消耗量，求出各分项工程人工、材料、施工机具台班消耗数量并汇总成单位工程所需各类人工工日、材料和施工机具台班的消耗量； ②采用实物量法，采用的是当时当地的各类人工工日、材料、施工机械台班、施工仪器仪表台班的实际单价分别乘以相应的人工工日、材料和施工机具台班总的消耗量，汇总后得出单位工程的直接费。 由此判断，实物量法与工料单价法编制预算，其工作步骤的差异体现在直接费的计算。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]