[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898023":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},898023,582,1,"单选题","(2018年)用工料单价法计算建筑安装工程费时需套用定额预算单价，下列做法正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","分项工程名称与定额名称完全一致时，直接套用定额预算单价",false,{"key":16,"text":17,"correct":14},"B","分项工程计量单位与定额计量单位完全一致时，直接套用定额预算单价",{"key":19,"text":20,"correct":14},"C","分项工程主要材料品种与预算定额不一致时，直接套用定额预算单价",{"key":22,"text":23,"correct":24},"D","分项工程施工工艺条件与预算定额不一致时，调整定额预算单价后套用",true,"分项工程的名称、规格、计量单位与预算单价或单位估价表中所列内容完全一致时，可以直接套用预算单价，三者应同时满足才可直接套用，AB 选项表述不完整。分项工程的主要材料品种与预算单价或单位估价表中规定材料不一致时，不可以直接套用预算单价，需要按实际使用材料价格换算预算单价，C 错。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]