[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898022":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},898022,582,1,"单选题","(2018年)采用全费用综合单价建筑施工图预算，下列说法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","综合单价应由人材机费、管理费、综合计取的措施项目费、规费和税金构成",false,{"key":16,"text":17,"correct":18},"B","可以计量的措施项目费与分部分项工程费的计算方法相同",true,{"key":20,"text":21,"correct":14},"C","人工费、材料费、施工机具使用费应按预算定额发布时期的价格确定",{"key":23,"text":24,"correct":14},"D","综合计取的措施项目费应以分部分项工程费为基数乘以相应费率计算","综合单价应由人材机费、管理费、利润、规费和税金构成，A 错；人工费、材料费、施工机具使用费应按预算定额编制时期的价格确定，C 错；综合计取的措施项目费应以分部分项工程费和可计量的措施项目费为基数乘以相应费率计算，D 错。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]