[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898016":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},898016,582,1,"单选题","(2010年)应用预算单价法编制施工图预算时，在套用定额单价后，紧接的工作是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","计算工程量",false,{"key":16,"text":17,"correct":18},"B","工料分析",true,{"key":20,"text":21,"correct":14},"C","编写编制说明",{"key":23,"text":24,"correct":14},"D","计算造价","预算中建筑安装工程费的计算程序",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]