[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898003":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898003,582,1,"单选题","（2019年真题）某地市政道路工程,已知与其类似已完工程造价指标为600元\u002Fm2，人、材、机占工程造价10%、50%、20%,拟建工程与类似工程人、材、机差异系数为1.1、1.05、1.05。假定以人、材、机为基数取费，综合费率为25%，则该工程综合单价为（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","507",false,{"key":16,"text":17,"correct":14},"B","608.4",{"key":19,"text":20,"correct":21},"C","633.75",true,{"key":23,"text":24,"correct":14},"D","657","P155-166 该工程综合单价=600（10%*1.1+50%*1.05+20%*1.05）*（1+25%）=633.75元\u002Fm2",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]