[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898001":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898001,582,1,"单选题","(2018年)采用概算定额法编制设计概算的主要工作有：①列出分部分项工程项目名称并计算工程量；②搜集基础资料；③编写概算编制说明；④计算措施项目费；⑤确定各分部分项工程费；⑥汇总单位工程概算造价。下列工作排序正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","②①⑤④⑥③",true,{"key":16,"text":17,"correct":18},"B","②③①⑤④⑥",false,{"key":20,"text":21,"correct":18},"C","③②①④⑤⑥",{"key":23,"text":24,"correct":18},"D","②①③⑤④⑥","概算定额法编制设计概算的步骤如下：（1）搜集基础资料、熟悉设计图纸和了解有关施工条件和施工方法。（2）按照概算定额子目，列出单位工程中分部分项工程项目名称并计算工程量。（3）确定各分部分项工程费。（4）计算措施项目费。（5）计算汇总单位工程概算造价：（6）编写概算编制说明。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]