[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897991":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},897991,582,1,"单选题","(2013年)照国家有关规定，作为年度固定资产投资计划、计划投资总额及构成数额的编制和确定依据的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","经批准的投资估算",false,{"key":16,"text":17,"correct":18},"B","经批准的设计概算",true,{"key":20,"text":21,"correct":14},"C","经批准的施工图预算",{"key":23,"text":24,"correct":14},"D","经批准的工程决算","设计概算是编制固定资产投资计划、确定和控制建设项目投资的依据。设计概算投资应包括建设项目从立项、可行性研究、设计、施工、试运行到竣工验收等的全部建设资金。按照国家有关规定，编制年度固定资产投资计划，确定计划投资总额及其构成数额，要以批准的初步设计概算为依据，没有批准的初步设计文件及其概算，建设工程不能列人年度固定资产投资计划。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]