[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897989":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},897989,582,1,"单选题","(2013年)工业项目总平面设计中，影响工程造价的主要因素包括()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","现场条件、占地面积、功能分区、运输方式",true,{"key":16,"text":17,"correct":18},"B","现场条件、产品方案、运输方式、柱网布置",false,{"key":20,"text":21,"correct":18},"C","占地面积、功能分区、空间组合、建筑材料",{"key":23,"text":24,"correct":18},"D","功能分区、空间组合、设备选型、厂址方案","总平面设计中影响工程造价的主要因素包括：现场条件、占地面积、功能分区、运输方式。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]