[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897969":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},897969,582,1,"单选题","(2018年)关于建设项目投资估算的编制，下列说法正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","应直接委托造价工程师编制",false,{"key":16,"text":17,"correct":14},"B","应做到费用构成齐全，并适当降低估算标准，节省投资",{"key":19,"text":20,"correct":14},"C","项目建设书阶段的投资估算精度误差应控制在±20%以内",{"key":22,"text":23,"correct":24},"D","应对影响造价变动的因素进行敏感性分析",true,"应委托有相应工程造价咨询资质的单位编制，A 错；应做到工程内容和费用构成齐全，不漏项，不提高或降低估算标准，计算合理，不少算、不重复计算，B 错；项目建设书阶段的投资估算精度误差应控制在±30%以内，C 错。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]