[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897964":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},897964,582,1,"单选题","(2015年)投资估算的主要工作包括：①估算预备费；②估算工程建设其他费；③估算工程费用；④估算设备购置费。其正确的工作步骤是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","③④②①",false,{"key":16,"text":17,"correct":14},"B","③④①②",{"key":19,"text":20,"correct":21},"C","④③②①",true,{"key":23,"text":24,"correct":14},"D","④③①②","本题考查的是投资估算的编制。投资估算编制的具傩体流程图如下， @##",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]