[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897929":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},897929,582,1,"单选题","(2009年)某工程在建设期初预计和建设期第一年末实际发生的设备、工器具购置情况如下表所示。与建设期初相比，第一年末的设备、工器具价格指数为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.9802",false,{"key":16,"text":17,"correct":18},"B","1.0811",true,{"key":20,"text":21,"correct":14},"C","1.1072",{"key":23,"text":24,"correct":14},"D","1.197","本题考核的是设备、工器具价格指数的计算根据公式：设备、工器具价格指数=∑(报告期设备工器具单价×报告期购置数量)\u002F∑(基期设备工器具单价×报告期购置数量)，则第一年末的设备、工器具价格指数=(110*5+78*8+48*12+10*65)\u002F(100*5+75*8+50*12+8*65)=2400\u002F2220≈1.0811",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]