[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897923":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},897923,582,1,"单选题","(2018年)编制某分项工程预算定额人工工日消耗量时,已知基本用工,辅助用工、超运距用工分别为20工日、2 工日、3 工日,人工幅度差系数为10%,则该分项工程单位人工工日消耗量为（ ）工日。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","27.0",false,{"key":16,"text":17,"correct":14},"B","27.2",{"key":19,"text":20,"correct":14},"C","27.3",{"key":22,"text":23,"correct":24},"D","27.5",true,"（20+2+3）×（1+10%）=27.5（工日）",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]