[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897919":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},897919,582,1,"单选题","(2014年)完成某单位分部分项工程需要基本用工4.2工日，超运距用工0.3工日，辅助用工1工日，人工幅度系数为10%，则该单位分部分项工作预算定额人工消耗量为（）工日。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","5.92",false,{"key":16,"text":17,"correct":14},"B","5.95",{"key":19,"text":20,"correct":14},"C","6.02",{"key":22,"text":23,"correct":24},"D","6.05",true,"预算定额中人工工日消耗量是指在正常施工条件下，生产单位合格产品所必需消耗的人工工日数量，是由分项工程所综合的各个工序劳动定额包括的基本用工、 其他用工两部分组成的。其他用工是辅助基本用工消耗的工日，包括超运距用工、辅助用工和人工幅度差用工。人工幅度差=(基本用工+辅助用工+超运距用工）× 人工幅度差系数。预算定额人工消耗量=（4.2+0.3+1）×（1+10%）=6.05",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]