[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897918":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},897918,582,1,"单选题","(2013年)下列工程项目总投资构成项中，应计入单项工程投资估算指标中的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","生产家具购置费",true,{"key":16,"text":17,"correct":18},"B","基本预备费",false,{"key":20,"text":21,"correct":18},"C","涨价预备费",{"key":23,"text":24,"correct":18},"D","铺底流动资金","投资估算指标中，单项工程指标包括建筑工程费、安装工程费、设备、工器具及生产家具购置费和可能包含的其他费用。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]