[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897915":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},897915,582,1,"单选题","(2010年)根据单项工程的一般划分原则，下列单项工程中属于辅助生产设施的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","废水处理站",false,{"key":16,"text":17,"correct":14},"B","水塔",{"key":19,"text":20,"correct":21},"C","机修车间",true,{"key":23,"text":24,"correct":14},"D","职工医院","(2)辅助生产设施。为主要生产车间服务的工程项目。包括集中控制室、中央实验室、机修、电修、仪器仪表修理及木工（模）等车间，原材料、半成品、成品及危险品等仓库。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]