[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897914":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},897914,582,1,"单选题","(2015年)在正常施工条件下，完成10m3混凝土梁浇捣需4个基本用工，0.5个辅助用工，0.3个超运距用工，若人工幅度差系数为10%，则该梁混凝土浇捣预算定额人工消耗量为( )工日\u002F10m3。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","5.20",false,{"key":16,"text":17,"correct":14},"B","5.23",{"key":19,"text":20,"correct":14},"C","5.25",{"key":22,"text":23,"correct":24},"D","5.28",true,"该题主要考察的是：定额人工消耗量的计算 “预算定额中人工 工日消耗量是由分项工 程所综合的各个工序 劳动定额包括的基本用工、其他用工两部分组成的。人工幅度差=（基本用工+辅助用工+超运距用工）*人工幅度差系数=(4+0.5+0.3)x10%=0.48；预算定额人工消耗量=基本用工+（超运距用工+辅助用工+人工幅度差）=4(0.5+0.3+0.48)=5.28工日\u002F10m3。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]