[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897913":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},897913,582,1,"单选题","(2016年)完成某分部分项工程1m3需基本用工0.5工日，超运距用工0.05工日，辅助用工0.1工日。如人工幅度差系数为10%，则该工程预算定额人工工日消耗量为()供给\u002F10m3。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","6.05",false,{"key":16,"text":17,"correct":14},"B","5.85",{"key":19,"text":20,"correct":14},"C","7.00",{"key":22,"text":23,"correct":24},"D","7.15",true,"预算定额中人工工日消耗量是指在正常施工条件下，生产单位合格产品所必需消耗的人工工日数量，是由分项工程所综合的各个工序劳动定额包括的基本用工、其他用工两部分组成的。 (2)其他用工。其他用工是辅助基本用工消耗的工日，包括超运距用工、辅助用工和人工幅度差用工。 人工幅度差=(基本用工+辅助用工+超运距用工)×人工幅度差系数人工幅度差用工：(0.5+0.05+0.1)×10%=0.065(0.5+0.05+0.1+0.065)×10=7.15",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]