[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897912":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},897912,582,1,"单选题","(2014年)某挖土机挖土一次正常循环工作时间为50s，每次循环平均挖土量为0.5m3，机械正常利用系数为0.8，机械幅度差系数为25%，按8小时工作制考虑，挖土方预算定额的机械台班消耗量为（）台班\u002F1000m3。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5.43",true,{"key":16,"text":17,"correct":18},"B","7.2",false,{"key":20,"text":21,"correct":18},"C","8",{"key":23,"text":24,"correct":18},"D","8.68","机械纯工作1小时的循环次数=3600\u002F50=72(次\u002F台时) 机械纯工作1小时的生产率=72×0.5=36 机械台班产量定额=36×8×0.8=230.4 台班时间定额=1\u002F230.4=0.00434 耗用台班=0.00434×（1+0.25）=0.00543。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]