[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897902":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},897902,582,1,"单选题","(2018年)已知某人工抹灰10m2 的基本工作时间为4 小时,辅助工作时间占工序作业时间的5%,准备与结束工作时间、不可避免的中断时间、休息时间分别占工作日的6%、11%、3%。则该人工抹灰的时间定额为（ ）工日\u002F100m2",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","6.30",false,{"key":16,"text":17,"correct":14},"B","6.56",{"key":19,"text":20,"correct":21},"C","6.58",true,{"key":23,"text":24,"correct":14},"D","6.67","基本工作时间=4h=0.5（工日\u002F10㎡）工序作业时间=0.5\u002F（1-5%）=0.526（工日\u002F10㎡）时间定额=0.526\u002F（1-6%-11%-3%）=0.658（工日\u002F10㎡）=6.58（工日\u002F100m2）",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]