[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897897":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},897897,582,1,"单选题","(2017年)已知人工挖某土方1m3的基本工作时间为1个工作日，辅助工作时间占工序作业时间的5%，准备与结束工作时间、不可避免的中断时间、休息时间分别占工作日的3%、2%、15%，该人工挖土的时间定额为（）工日\u002F10m3。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","13.33",false,{"key":16,"text":17,"correct":18},"B","13.16",true,{"key":20,"text":21,"correct":14},"C","13.13",{"key":23,"text":24,"correct":14},"D","12.50","本题考查的是确定人工定额消耗量的基本方法。 工序作业时间=基本工作时间\u002F（1-辅助时间%）=1\u002F（1-5%）=1.053（工日\u002Fm3） 时间定额=工序作业时间\u002F（1-规范时间%）=1.053\u002F（1-3%-2%-15%）=1.316（工日\u002Fm3）=13.16（工日\u002F10m3）。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]