[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897896":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},897896,582,1,"单选题","(2016年)若完成1m3墙体砌筑工作的基本工时为0.5工日，辅助工作时间占工序时间的4%，准备与结束工作时间、不可避免的中断时间、休息时间分别占工作时间的6%、3%和12%，该工程时间定额为()工日\u002Fm3。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","0.581",false,{"key":16,"text":17,"correct":14},"B","0.608",{"key":19,"text":20,"correct":14},"C","0.629",{"key":22,"text":23,"correct":24},"D","0.659",true,"工序作业时间 =基本工作时间+辅助工作时间=基本工作时间\u002F（1-辅助时间％）=0.5\u002F(1-4%)=0.521，规范时间 = 准备与结束工作时间+不可避免的中断时间+休息时间，定额时间=工序作业时间\u002F(1-规范时间%）=0.521\u002F（1-6%-3%-12%）=0.659",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]