[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897890":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},897890,582,1,"单选题","(2013年)下列工人工作时间消耗中，属于有效工作时间的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","因混凝土养护引起的停工时间",false,{"key":16,"text":17,"correct":14},"B","偶然停工（停水、停电）增加的时间",{"key":19,"text":20,"correct":14},"C","产品质量不合格返工的工作时间",{"key":22,"text":23,"correct":24},"D","准备施工工具花费的时间",true,"有效工作时间包括基本工作时间、辅助工作时间、准备与结束工作时间的消耗，其中D选项属于准备与结束工作时间。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]