[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897889":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},897889,582,1,"单选题","(2012年)关于施工机械安拆费和场外运费的说法，正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","安拆费指安拆一次所需的人工，材料和机械使用费之和",false,{"key":16,"text":17,"correct":18},"B","安拆费中包括机械辅助设施的折旧费",true,{"key":20,"text":21,"correct":14},"C","能自行开动机械的安拆费不予计算",{"key":23,"text":24,"correct":14},"D","塔式起重机安拆费的超高增加费应计入机械台班单价","A表述的是一次安拆费的概念。安拆费指施工机械在现场进行安装与拆卸所需的人工、材料、机械和试运转费用以及机械辅助设施的折旧、搭设、拆除等费用。C应是不需安装、拆卸且自身又能开行的机械和固定在车间不需安装、拆卸及运输的机械，其安拆费及场外运费不计算。D塔式起重机安拆费的超高增加费，各地区可根据具体情况确定。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]