[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897886":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},897886,582,1,"单选题","(2016年)下列机械工作时间中，属于有效工作时间的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","筑路机在工作区末端的掉头时间",false,{"key":16,"text":17,"correct":18},"B","体积达标而未达到载重吨位的货物汽车运输时间",true,{"key":20,"text":21,"correct":14},"C","机械在工作地点之间的转移时间",{"key":23,"text":24,"correct":14},"D","装车数量不足而在低负荷下工作的时间","有效工作的时间消耗中又包括正常负荷下、有根据地降低负荷下的工时消耗。有根据地降低负荷下的工作时间，是在个别情况下由于技术上的原因，机器在低于其计算负荷下工作的时间。例如，汽车运输重量轻而体积大的货物时，不能充分利用汽车的载重吨位因而不得不降低其计算负荷。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]