[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897885":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},897885,582,1,"单选题","(2015年)某出料容量750L的混凝土搅拌机，每循环一次的正常延续时间为9分钟，机械正常利用系数为0.9。按8小时工作制考虑，该机械的台班产量定额为( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","36m3\u002F台班",true,{"key":16,"text":17,"correct":18},"B","40m3\u002F台班",false,{"key":20,"text":21,"correct":18},"C","0.28台班\u002Fm3",{"key":23,"text":24,"correct":18},"D","0.25台班\u002Fm3","本题考查的是确定机械台班定额消耗量的基本方法。施工机械台班产量定额=机械1h纯工作正常生产率×工作班延续时间×机械时间利用系数正常延续时间为9min=0.15h, 该搅拌机纯工作1h循环次数=1\u002F0.15=6.67次；该搅拌机纯工作1h正常生产率=6.67x750=5002.5L=5.0025m3,该机械的台班产量定额=5.0025x8x0.9=36.02m3。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]