[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897881":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},897881,582,1,"单选题","(2013年)通过计时观察，完成某工程的基本工时为6h\u002Fm，辅助工作时间为工序作业时间的8%，规范时间占工作时间的15%，则完成该工程的时间定额是()工日\u002Fm3。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","0.93",false,{"key":16,"text":17,"correct":14},"B","0.94",{"key":19,"text":20,"correct":14},"C","0.95",{"key":22,"text":23,"correct":24},"D","0.96",true,"基本工作时间=6小时=0.75（工日\u002Fm3）；工序作业时间=0.75\u002F(1-8%)=0.815；时间定额=0.815\u002F(1-15%)=0.96工日\u002Fm3。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]