[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897878":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},897878,582,1,"单选题","(2018年)关于工程量清单计价建设范围，下列说法正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","达到或超过规定建设规模的工程,必须采用工程量清单计价",false,{"key":16,"text":17,"correct":14},"B","达到或超过规定建设数额的工程,必须采用工程量清单计价",{"key":19,"text":20,"correct":14},"C","国有资金占投资总额不足50%的建设工程发承包,不必采用工程量清单计价",{"key":22,"text":23,"correct":24},"D","不采用工程量清单计价的建设工程,应执行计价规范中除工程量清单等专门性规定以外的规定",true,"使用国有资金投资的建设工程发承包，必须采用工程量清单计价，AB 错误；国有资金（含国家融资资金）为主的工程建设项目是指国有资金占投资总额50%以上，或虽不足50%但国有投资者实质上拥有控股权的工程建设项目，必须采用工程量清单计价，C 错误。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]