[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897872":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},897872,582,1,"单选题","(2014年)编制工程量清单出现计算规范附录中未包括的清单项目时，编制人应作补充，下列有关编制补充项目的说法中正确的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","补充项目编码应由B与三位阿拉伯数字组成",false,{"key":16,"text":17,"correct":14},"B","补充项目应报县级工程造价管理机构备案",{"key":19,"text":20,"correct":21},"C","补充项目的工作内容应予以明确",true,{"key":23,"text":24,"correct":14},"D","补充项目编码应顺序编制，起始序号有编制人根据需要自主确定","补充项目的编码由计量规范的代码与B和三维阿拉伯数字组成，所以A错；将编制的补充项目报省级或行业工程造价管理机构备案，所以B错；在工程量清单中应附补充项目的项目名称、项目特征、计量单位、工程量计算规则和工作内容，所以C正确；补充项目编码应从001起顺序编制，所以D错。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]