[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897870":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},897870,582,1,"单选题","(2010年)采用工程量清单计价方式招标时，对工程量清单的完整性和准确性负责的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","编制招标文件的招标代理人",false,{"key":16,"text":17,"correct":14},"B","编制清单的工程造价咨询人",{"key":19,"text":20,"correct":21},"C","发布招标文件的招标人",true,{"key":23,"text":24,"correct":14},"D","确定中标的投标人","采用工程量清单方式招标，招标工程量清单必须作为招标文件的组成部分，其准确性和完整性由招标人负责。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]