[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897868":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},897868,582,1,"单选题","(2016年)对于不能计量工程量的措施项目，当按施工方案计算措施费时，若无“计算基础”和“费率”数值，则()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","以定额基价为计算基础，以国家、行业、地区定额中相应的费率计算金额",false,{"key":16,"text":17,"correct":14},"B","以“定额人工费+定额机械费”为计算基础，以国家、行业、地区定额中相应费率计算金额",{"key":19,"text":20,"correct":21},"C","只填写“金额”数值，在备注中说明施工方案出处或计算方法",true,{"key":23,"text":24,"correct":14},"D","以备注中说明的计算方法，补充填写“计算基础”和“费率”","按施工方案计算的措施费，若无“计算基础”和“费率”的数值，也可只填“金额”数值，但应在备注栏说明施工方案出处或计算方法。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]