[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897867":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},897867,582,1,"单选题","(2015年)关于总承包服务费的支付，下列说法中正确的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设单位向总承包单位支付",true,{"key":16,"text":17,"correct":18},"B","分包单位向总承包单位支付",false,{"key":20,"text":21,"correct":18},"C","专业承包单位向总承包单位支付",{"key":23,"text":24,"correct":18},"D","专业承包单位向建设单位支付","该题主要考察的是：总承包服务费的内容，“招标人应预计该项费用并按投标人的投标报价向投标人支付该项费用。”",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]