[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897865":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},897865,582,1,"单选题","(2014年)招标人在工程量清单中提供的用于支付必然发生但暂不能确定价格的材料、工程设备价及专业工程金额是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","暂列金额",false,{"key":16,"text":17,"correct":18},"B","暂估价",true,{"key":20,"text":21,"correct":14},"C","总承包服务费",{"key":23,"text":24,"correct":14},"D","价差预备费","暂估价是指招标人在工程量清单中提供的用于支付必然发生但暂时不能确定价格的材料、工程设备以及专业工程的金额，包括材料暂估单价、工程设备暂估单价、专业工程暂估价。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]