[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897858":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},897858,582,1,"单选题","(2018年)关于工程造价的分布组合计价原理，下列说法正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","分部分项工程费=基本构造单元工程量×工料单价",false,{"key":16,"text":17,"correct":14},"B","工料单价指人工、材料和施工机械台班单价",{"key":19,"text":20,"correct":14},"C","基本构造单元是由分部工程适当组合形成",{"key":22,"text":23,"correct":24},"D","工程总价是按规定程序和方法逐级汇总形成的工程造价",true,"分部分项工程费=基本构造单元工程量×相应单价，A 错误；工料单价仅包括人工、材料、机具使用费用，是各种人工消耗量、各种材料消耗量、各类施工机具台班消耗量与其相应单价的乘积，B 错误；基本构造单元是由分项工程适当组合形成，C 错误。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]