[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897857":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},897857,582,1,"单选题","(2018年)反映完成一定计量单位合格扩大结构构件需消耗的人工、材料和施工机具台班数量的定额是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","概算指标",false,{"key":16,"text":17,"correct":18},"B","概算定额",true,{"key":20,"text":21,"correct":14},"C","预算定额",{"key":23,"text":24,"correct":14},"D","施工定额","概算定额是完成单位合格扩大分项工程或扩大结构构件所需消耗的人工、材料和施工机具台班的数量及其费用标准。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]