[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897851":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},897851,582,1,"单选题","(2015年)依法必须采用工程量清单招标的建设项目，投标人需要采用而招标人不需采用的计价依据是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","国家、地区或行业定额资料",false,{"key":16,"text":17,"correct":14},"B","工程造价信息、资料和指数",{"key":19,"text":20,"correct":14},"C","计价活动相关规章课程",{"key":22,"text":23,"correct":24},"D","企业定额",true,"该题主要考察的是：工程量清单的编制，",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]