[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897846":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},897846,582,1,"单选题","(2013年)下列关于工程计价的说法中，正确的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程计价包含计算工程量和套定额两个环节",false,{"key":16,"text":17,"correct":14},"B","建筑安装工程费=∑基本构造单元工程量×相应单价",{"key":19,"text":20,"correct":21},"C","工程计价包括工程单价的确定和总价的计算",true,{"key":23,"text":24,"correct":14},"D","工程计价中的工程单价仅指综合单价","工程计价包括单价的确定和总价的计算。①工程单价是指完成单位工程基本构造单元的工程量所需要的基本费用。工程单价包括工料单价和综合单价。②工程总价是指经过规定的程序或办法逐级汇总形成的相应工程造价。 分部分项工程费(或措施项目费)=∑[基本构造单元工程量(定额项目或清单项目)×相应单价]",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]