[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897842":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},897842,582,1,"单选题","（2019年真题）根据我国现行建设项目总投资及工程造价组成，工程概算阶段考虑的对一般自然灾害处理的费用,应包含在（ ）内。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","未明确项目准备金",false,{"key":16,"text":17,"correct":18},"B","工程建设不可预见费",true,{"key":20,"text":21,"correct":14},"C","暂列金额",{"key":23,"text":24,"correct":14},"D","不可预见准备金","P30-31 基本预备费是指投资估算或工程概算阶段预留的，由于工程实施中不可预见的工程变更及洽商、一般自然灾害处理、地下障碍物处理、超规超限设备运输等而可能增加的费用，亦可称为工程建设不可预见费。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]