[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897841":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},897841,582,1,"单选题","（2019年真题）某新建项目，建设期为2年,分年均衡进行贷款，第一年贷款200万元，第二年贷款300万元，贷款利息只计息不支付，年利率为10%的情况下，该项目应计建设期贷款利息为（）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","36.00",false,{"key":16,"text":17,"correct":18},"B","46.00",true,{"key":20,"text":21,"correct":14},"C","52.00",{"key":23,"text":24,"correct":14},"D","70.00","P31-32 根据建设期利息的计算公式 第一年贷款利息为：（200\u002F2）*10%=10万元 第二年贷款利息为：（200+10+300\u002F2）*10%=36万元 该项目应计建设期贷款利息为：10+36=46万元",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]