[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897824":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},897824,582,1,"单选题","(2018年)关于建设项目场地准备和建设单位临时设施费的计算,下列说法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","改扩建项目一般应计工程费用和拆除清理费",false,{"key":16,"text":17,"correct":18},"B","凡可回收材料的拆除工程应采用以料抵工方式冲抵拆除清理费",true,{"key":20,"text":21,"correct":14},"C","新建项目应根据实际工程量计算，不按工程费用的比例计算",{"key":23,"text":24,"correct":14},"D","新建项目应按工程费用比例计算，不根据实际工程量计算","改扩建项目一般只计拆除清理费，A 错误；新建项目的场地准备和临时设施费应根据实际工程量估算，或按工程费用的比例计算，CD 错误。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]