[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897799":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},897799,582,1,"单选题","(2015年)根据我国现行建筑安装工程费项目组成的规定，下列费用应列入暂列金额的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工过程中可能发生的工程变更及索赔、现场签证等费用",true,{"key":16,"text":17,"correct":18},"B","应建设单位要求，完成建设项目之外的零星项目费用",false,{"key":20,"text":21,"correct":18},"C","对建设单位自行采购的材料进行保管所发生的费用",{"key":23,"text":24,"correct":18},"D","施工用电、用水的开办费","该题主要考察的是：暂列金额所包含的内容， “暂列金额是指建设单位在工程量清单中暂定并包括在工程合同价款中的一笔款项。用于施工合同签订时尚未确定或者不可预见的所需材料、工程设备、服务的采购，施工中可能发生的工程变更、合同约定调整因素出现时的工程价款调整以及发生的索赔、现场签证确认等的费用”",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]