[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897773":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},897773,582,1,"单选题","(2018年)根据现行建设项目投资构成相关规定，固定资产投资应与（ ）相对应。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程费用+工程建设其他费用",false,{"key":16,"text":17,"correct":18},"B","建设投资+建设期利息",true,{"key":20,"text":21,"correct":14},"C","建设安装工程费+设备及工器具购置费",{"key":23,"text":24,"correct":14},"D","建设项目总投资","其中建设投资和建设期利息之和对应于固定资产投资，固定资产投资与建设项目的工 程造价在量上相等。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]