[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"lib-581-39":3},{"library":4,"page":9,"limit":10,"total":11,"questions":12,"related":615},{"id":5,"name":6,"category":7,"favorite":8},581,"建设工程造价管理基础知识","建筑工程",0,39,50,2873,[13,34,46,58,70,82,94,106,118,130,142,154,166,178,190,202,214,226,238,250,262,274,286,298,310,322,334,346,358,370,382,394,406,418,426,438,450,462,474,486,498,508,520,531,543,555,567,579,591,603],{"id":14,"libraryId":5,"type":15,"typeLabel":16,"stem":17,"options":18,"answer":24,"analysis":33},896775,1,"单选题","关于保证(保修)金使用及返还的叙述不正确的是（ ）。",[19,23,27,30],{"key":20,"text":21,"correct":22},"A","缺陷责任期内，承包人应认真履行合同约定的责任",false,{"key":24,"text":25,"correct":26},"B","承包人维修并承担相应费用后，免除对工程的一般损失赔偿责任",true,{"key":28,"text":29,"correct":22},"C","承包人已经提供履约担保的，发包人不得同时预留工程质量保证金",{"key":31,"text":32,"correct":22},"D","经查明属他人原因造成的缺陷，发包人负责组织维修，承包人不承担费用","",{"id":35,"libraryId":5,"type":15,"typeLabel":16,"stem":36,"options":37,"answer":24,"analysis":33},896776,"《建筑工程施工合同(示范文本)》合同文件执行的优先顺序是（ ）。",[38,40,42,44],{"key":20,"text":39,"correct":22},"合同协议书→合同通用条款→合同专用条款→技术标准和要求→已标价工程量清单或预算书",{"key":24,"text":41,"correct":26},"合同协议书→合同专用条款→合同通用条款→技术标准和要求→已标价工程量清单或预算书",{"key":28,"text":43,"correct":22},"技术标准和要求→合同协议书→合同专用条款→合同通用条款→已标价工程量清单或预算书",{"key":31,"text":45,"correct":22},"技术标准和要求→合同协议书→已标价工程量清单或预算书→合同通用条款→合同专用条款",{"id":47,"libraryId":5,"type":15,"typeLabel":16,"stem":48,"options":49,"answer":31,"analysis":33},896777,"下列各项中合同解释排列顺序正确的是（ ）。",[50,52,54,56],{"key":20,"text":51,"correct":22},"合同协议书→通用条款→专用条款→中标通知书",{"key":24,"text":53,"correct":22},"图纸→专用条款→通用条款→中标通知书",{"key":28,"text":55,"correct":22},"已标价工程量清单→专用条款→通用条款→技术规范",{"key":31,"text":57,"correct":26},"合同协议书→投标函→专用条款→通用条款",{"id":59,"libraryId":5,"type":15,"typeLabel":16,"stem":60,"options":61,"answer":31,"analysis":33},896778,"承包人应在知道或应当知道索赔事件发生后（ ）天内，向监理人递交索赔意向通知书。",[62,64,66,68],{"key":20,"text":63,"correct":22},"7",{"key":24,"text":65,"correct":22},"14",{"key":28,"text":67,"correct":22},"21",{"key":31,"text":69,"correct":26},"28",{"id":71,"libraryId":5,"type":15,"typeLabel":16,"stem":72,"options":73,"answer":24,"analysis":33},896779,"在具备施工条件的前提下，发包人应在双方签订合同后一个月内或不迟于约定开工日期前（ ）内预付工程备料款。",[74,76,78,80],{"key":20,"text":75,"correct":22},"10天",{"key":24,"text":77,"correct":26},"7天",{"key":28,"text":79,"correct":22},"15天",{"key":31,"text":81,"correct":22},"20天",{"id":83,"libraryId":5,"type":15,"typeLabel":16,"stem":84,"options":85,"answer":28,"analysis":33},896780,"由于发包人原因导致工程无法按规定期限竣(交)工验收的，在承包人提交竣(交)工验收报告（ ）天后，工程自动进入缺陷责任期。",[86,88,90,92],{"key":20,"text":87,"correct":22},"30",{"key":24,"text":89,"correct":22},"60",{"key":28,"text":91,"correct":26},"90",{"key":31,"text":93,"correct":22},"120",{"id":95,"libraryId":5,"type":15,"typeLabel":16,"stem":96,"options":97,"answer":20,"analysis":33},896781,"由于承包人原因造成某项缺陷或损坏，使某项工程或工程设备不能按原定目标使用而需要再次检查、检验和修复的，发包人有权要求承包人相应延长缺陷责任期，但缺陷责任期最长不超过（ ）年。",[98,100,102,104],{"key":20,"text":99,"correct":26},"2",{"key":24,"text":101,"correct":22},"3",{"key":28,"text":103,"correct":22},"5",{"key":31,"text":105,"correct":22},"6",{"id":107,"libraryId":5,"type":15,"typeLabel":16,"stem":108,"options":109,"answer":28,"analysis":33},896782,"缺陷责任期的开始计算日期为（ ）。",[110,112,114,116],{"key":20,"text":111,"correct":22},"工程完工之日",{"key":24,"text":113,"correct":22},"提交竣工验收申请之日",{"key":28,"text":115,"correct":26},"通过竣工验收之日",{"key":31,"text":117,"correct":22},"通过竣工验收后30天",{"id":119,"libraryId":5,"type":15,"typeLabel":16,"stem":120,"options":121,"answer":20,"analysis":33},896783,"某建筑工程钢筋综合用量1000t。施工合同中约定，结算时对钢筋综合价格涨幅±5%以上部分依据造价处发布的基准价调整价格差额。承包人投标报价2400元\u002Ft，投标期、施工期造价管理机构发布的钢筋综合基准价格分别为2500元\u002Ft、2800元\u002Ft，则需调增钢筋材料费用为（ ）万元。",[122,124,126,128],{"key":20,"text":123,"correct":26},"17.5",{"key":24,"text":125,"correct":22},"28.0",{"key":28,"text":127,"correct":22},"30.0",{"key":31,"text":129,"correct":22},"40.0",{"id":131,"libraryId":5,"type":15,"typeLabel":16,"stem":132,"options":133,"answer":24,"analysis":33},896784,"某施工合同约定采用价格指数及价格调整公式调整价格差额，调价因素及有关数据见下表。某月完成进度款为1500万元，则该月应当支付给承包人的价格调整金额为（ ）万元。",[134,136,138,140],{"key":20,"text":135,"correct":22},"-30.3",{"key":24,"text":137,"correct":26},"36.45",{"key":28,"text":139,"correct":22},"112.5",{"key":31,"text":141,"correct":22},"130.5",{"id":143,"libraryId":5,"type":15,"typeLabel":16,"stem":144,"options":145,"answer":28,"analysis":33},896785,"根据《建设工程施工合同（示范文本）》，关于安全文明施工费，下列说法错误的是（ ）。",[146,148,150,152],{"key":20,"text":147,"correct":22},"发包人应在开工后28天内预付安全文明施工费总额的50%，其余部分与进度款同期支",{"key":24,"text":149,"correct":22},"承包人对安全文明施工费应专款专用，不得挪作他用",{"key":28,"text":151,"correct":26},"发包人逾期支付安全文明施工费超过14天的，承包人有权向发包人发出要求预付的催告通知",{"key":31,"text":153,"correct":22},"安全文明施工费由发包人承担，发包人不得以任何形式扣减该部分费用",{"id":155,"libraryId":5,"type":15,"typeLabel":16,"stem":156,"options":157,"answer":28,"analysis":33},896786,"根据合同通用条款规定的文件解释优先顺序，下列文件中具有最优先解释权的是（ ）。",[158,160,162,164],{"key":20,"text":159,"correct":22},"规范标准",{"key":24,"text":161,"correct":22},"中标通知书",{"key":28,"text":163,"correct":26},"合同协议书",{"key":31,"text":165,"correct":22},"设计文件",{"id":167,"libraryId":5,"type":15,"typeLabel":16,"stem":168,"options":169,"answer":28,"analysis":33},896787,"由于承包人原因导致工期延误的，对于计划进度日期后续施工的工程，在使用价格调整公式时，现行价格指数应采用（ ）。",[170,172,174,176],{"key":20,"text":171,"correct":22},"计划进度日期的价格指数",{"key":24,"text":173,"correct":22},"实际进度日期的价格指数",{"key":28,"text":175,"correct":26},"A和B中较低者",{"key":31,"text":177,"correct":22},"A和B中较高者",{"id":179,"libraryId":5,"type":15,"typeLabel":16,"stem":180,"options":181,"answer":24,"analysis":33},896788,"关于施工承包合同中缺陷责任与保修的说法，正确的是（ ）。",[182,184,186,188],{"key":20,"text":183,"correct":22},"缺陷责任期自实际竣工日期起计算，最长不超过12个月",{"key":24,"text":185,"correct":26},"由他人原因造成的缺陷，发包人负责组织维修，承包人不承担费用，且发包人不得从保证金中扣除费用",{"key":28,"text":187,"correct":22},"因发包人原因导致工程无法按合同约定期限进行竣工验收的，缺陷责任期自竣工验收合格之日开始计算",{"key":31,"text":189,"correct":22},"发包人未经竣工验收擅自使用工程的，缺陷责任期自承包人提交竣工验收申请报告之日开始计算",{"id":191,"libraryId":5,"type":15,"typeLabel":16,"stem":192,"options":193,"answer":31,"analysis":33},896789,"按照索赔程序，承包人首先要完成的工作应当是（ ）。",[194,196,198,200],{"key":20,"text":195,"correct":22},"向发包人递交索赔报告",{"key":24,"text":197,"correct":22},"建立赔偿档案",{"key":28,"text":199,"correct":22},"确定判定索赔成立的原则",{"key":31,"text":201,"correct":26},"向发包人发出书面索赔意向通知",{"id":203,"libraryId":5,"type":15,"typeLabel":16,"stem":204,"options":205,"answer":31,"analysis":33},896790,"关于施工合同工程预付款，下列说法中正确的是（ ）。",[206,208,210,212],{"key":20,"text":207,"correct":22},"承包人预付款的担保金额通常高于发包人的预付款",{"key":24,"text":209,"correct":22},"发包人要求承包人提供预付款担保的，承包人应在发包人支付预付款14天前提供预付款担保",{"key":28,"text":211,"correct":22},"预付款的担保金额不会随着预付款的扣回而减少",{"key":31,"text":213,"correct":26},"预付款的支付按照专用合同条款约定执行，但最迟应在开工通知载明的开工日期7天前支付",{"id":215,"libraryId":5,"type":15,"typeLabel":16,"stem":216,"options":217,"answer":24,"analysis":33},896791,"下列在施工合同履行期间由不可抗力造成的损失中，应由承包人承担的是（ ）",[218,220,222,224],{"key":20,"text":219,"correct":22},"因工程损害导致的第三方人员伤亡",{"key":24,"text":221,"correct":26},"因工程损害导致的承包人人员伤亡",{"key":28,"text":223,"correct":22},"工程设备的损害",{"key":31,"text":225,"correct":22},"应监理人要求承包人照管工程的费用",{"id":227,"libraryId":5,"type":15,"typeLabel":16,"stem":228,"options":229,"answer":28,"analysis":33},896792,"某工程合同价为 300 万元， 本期完成合同价款 100 万元， 合同约定： 采用调值公式进行动态结算， 其中固定要素比重为 0.2， 调价要素分为 A、 B、 C 三类， 分别占合同价的比重为 0.15、 0.35、 0.3， 结算时价格指数分别增长了 20%、 15%、 25%， 则该工程需要调整的价款差额为（ ） 万元",[230,232,234,236],{"key":20,"text":231,"correct":22},"115.75",{"key":24,"text":233,"correct":22},"19.75",{"key":28,"text":235,"correct":26},"15.75",{"key":31,"text":237,"correct":22},"120.75",{"id":239,"libraryId":5,"type":15,"typeLabel":16,"stem":240,"options":241,"answer":31,"analysis":33},896793,"关于建设项目竣工结清阶段承包人索赔的权利和期限，下列说法中正确的是（ ）。",[242,244,246,248],{"key":20,"text":243,"correct":22},"承包人接受竣工结算支付证书后再无权提出任何索赔",{"key":24,"text":245,"correct":22},"承包人只能提出工程接收证书颁发前的索赔",{"key":28,"text":247,"correct":22},"承包人提出索赔的期限自缺陷责任期满时终止",{"key":31,"text":249,"correct":26},"承包人提出索赔的期限自接受最终支付证书时终止",{"id":251,"libraryId":5,"type":15,"typeLabel":16,"stem":252,"options":253,"answer":28,"analysis":33},896794,"编制工程量清单出现计算规范附录中未包括的清单项目时，编制人应做补充，下列有关编制补充项目的说法中正确的是（ ）。",[254,256,258,260],{"key":20,"text":255,"correct":22},"补充项目编码应由B与三位阿拉伯数字组成",{"key":24,"text":257,"correct":22},"补充项目应报县级工程造价管理机构备案",{"key":28,"text":259,"correct":26},"补充项目的工作内容应予以明确",{"key":31,"text":261,"correct":22},"补充项目编码应顺序编制，起始序号由编制人根据需要自主确定",{"id":263,"libraryId":5,"type":15,"typeLabel":16,"stem":264,"options":265,"answer":20,"analysis":33},896795,"措施项目清单编制中，下列适用于以“项”为单位计价的措施项目费是（ ）。",[266,268,270,272],{"key":20,"text":267,"correct":26},"已完工程及设备保护费",{"key":24,"text":269,"correct":22},"超高施工增加费",{"key":28,"text":271,"correct":22},"大型机械设备进出场及安拆费",{"key":31,"text":273,"correct":22},"施工排水、降水费",{"id":275,"libraryId":5,"type":15,"typeLabel":16,"stem":276,"options":277,"answer":28,"analysis":33},896796,"规费与增值税应按（ ）规定的计算。",[278,280,282,284],{"key":20,"text":279,"correct":22},"工程造价管理部门",{"key":24,"text":281,"correct":22},"国家或省级、国务院部委有关建设主管部门",{"key":28,"text":283,"correct":26},"国家或省级、行业建设主管部门",{"key":31,"text":285,"correct":22},"原规划管理部门和其他有关部门",{"id":287,"libraryId":5,"type":15,"typeLabel":16,"stem":288,"options":289,"answer":24,"analysis":33},896797,"关于建筑安装工程费用中的规费，下列说法中正确的是（ ）。",[290,292,294,296],{"key":20,"text":291,"correct":22},"规费是指有县级及以上有关权力部门规定必须缴纳或计取的费用",{"key":24,"text":293,"correct":26},"规费包括社会保险费和住房公积金",{"key":28,"text":295,"correct":22},"投标人在投标报价时填写的规费可高于规定的标准",{"key":31,"text":297,"correct":22},"社会保险费中包括建筑安装工程费一切险的投保费用",{"id":299,"libraryId":5,"type":15,"typeLabel":16,"stem":300,"options":301,"answer":24,"analysis":33},896798,"下列措施项目中宜采用分部(分项)工程量清单的方式编制的是（ ）。",[302,304,306,308],{"key":20,"text":303,"correct":22},"非夜间施工照明",{"key":24,"text":305,"correct":26},"施工排水、降水",{"key":28,"text":307,"correct":22},"已完工程及设备保护",{"key":31,"text":309,"correct":22},"二次搬运",{"id":311,"libraryId":5,"type":15,"typeLabel":16,"stem":312,"options":313,"answer":28,"analysis":33},896799,"关于规费的计算，下列说法正确的是（ ）。",[314,316,318,320],{"key":20,"text":315,"correct":22},"规费具有强制性，根据其组成又可细分为可竞争性的费用和不可竞争性的费用",{"key":24,"text":317,"correct":22},"规费由社会保险费和工程排污费组成",{"key":28,"text":319,"correct":26},"社会保险费包括养老保险费、失业保险费、医疗保险费、生育保险费、工伤保险费",{"key":31,"text":321,"correct":22},"规费由意外伤害保险费、住房公积金、工程排污费组成",{"id":323,"libraryId":5,"type":15,"typeLabel":16,"stem":324,"options":325,"answer":31,"analysis":33},896800,"工程量清单是招标文件的组成部分，工程量清单的组成不包括（ ）。",[326,328,330,332],{"key":20,"text":327,"correct":22},"分部分项工程工程量清单",{"key":24,"text":329,"correct":22},"措施项目清单",{"key":28,"text":331,"correct":22},"其他项目清单",{"key":31,"text":333,"correct":26},"直接工程费用清单",{"id":335,"libraryId":5,"type":15,"typeLabel":16,"stem":336,"options":337,"answer":20,"analysis":33},896801,"在工程量清单中，最能体现分部(分项)工程项目自身价值的本质是（ ）。",[338,340,342,344],{"key":20,"text":339,"correct":26},"项目特征",{"key":24,"text":341,"correct":22},"项目编码",{"key":28,"text":343,"correct":22},"项目名称",{"key":31,"text":345,"correct":22},"项目计量单位",{"id":347,"libraryId":5,"type":15,"typeLabel":16,"stem":348,"options":349,"answer":28,"analysis":33},896802,"使用国有资金投资项目的范围不包括（ ）。",[350,352,354,356],{"key":20,"text":351,"correct":22},"使用各级财政预算资金的项目",{"key":24,"text":353,"correct":22},"使用纳入财政管理的各种政府性专项建设基金的项目",{"key":28,"text":355,"correct":26},"使用国家发行债券所筹资金的项目",{"key":31,"text":357,"correct":22},"使用国有企业事业单位自有资金，并且国有资产投资者实际拥有控制权的项目",{"id":359,"libraryId":5,"type":15,"typeLabel":16,"stem":360,"options":361,"answer":24,"analysis":33},896803,"项目编码是分部(分项)工程量清单项目名称的数字标识，应采用（ ）位阿拉伯数字表示。",[362,364,366,368],{"key":20,"text":363,"correct":22},"13",{"key":24,"text":365,"correct":26},"12",{"key":28,"text":367,"correct":22},"11",{"key":31,"text":369,"correct":22},"10",{"id":371,"libraryId":5,"type":15,"typeLabel":16,"stem":372,"options":373,"answer":24,"analysis":33},896804,"关于工程量清单编制中的项目特征描述，下列说法中正确的是（ ）。",[374,376,378,380],{"key":20,"text":375,"correct":22},"措施项目无需描述项目特征",{"key":24,"text":377,"correct":26},"应按计算规范附录中规定的项目特征，结合技术规范、标准图集加以描述",{"key":28,"text":379,"correct":22},"对完成清单项目可能发生的具体工作和操作程序仍需加以描述",{"key":31,"text":381,"correct":22},"图纸中已有的工程规格、型号、材质等可不描述",{"id":383,"libraryId":5,"type":15,"typeLabel":16,"stem":384,"options":385,"answer":24,"analysis":33},896805,"根据《建设工程工程量清单计价规范》（GB50500-2013），一般不作为安全文明施工费计算基础的是（ ）。",[386,388,390,392],{"key":20,"text":387,"correct":22},"定额人工费",{"key":24,"text":389,"correct":26},"定额人工费＋定额材料费",{"key":28,"text":391,"correct":22},"定额人工费＋定额施工机具使用费",{"key":31,"text":393,"correct":22},"定额人工费＋定额材料费＋定额施工机具使用费",{"id":395,"libraryId":5,"type":15,"typeLabel":16,"stem":396,"options":397,"answer":28,"analysis":33},896806,"《建设工程工程量清单计价规范》规定，分部分项工程量清单项目编码的第三级为表示（ ）的顺序码。",[398,400,402,404],{"key":20,"text":399,"correct":22},"分项工程",{"key":24,"text":401,"correct":22},"扩大分项工程",{"key":28,"text":403,"correct":26},"分部工程",{"key":31,"text":405,"correct":22},"专业工程",{"id":407,"libraryId":5,"type":15,"typeLabel":16,"stem":408,"options":409,"answer":24,"analysis":33},896807,"根据《建设工程工程量清单计价规范》（GB50500-2013），关于工程量清单计价的有关要求，下列说法中正确的是（ ）。",[410,412,414,416],{"key":20,"text":411,"correct":22},"事业单位自有资金投资的建设工程发承包，可以不采用工程量清单计价",{"key":24,"text":413,"correct":26},"使用国有资金投资的建设工程发承包，必须采用工程量清单计价",{"key":28,"text":415,"correct":22},"国有资金投资总额占40%以上的项目，必须采用工程量清单计价",{"key":31,"text":417,"correct":22},"招标工程量清单的准确性和完整性由清单编制人负责",{"id":419,"libraryId":5,"type":15,"typeLabel":16,"stem":420,"options":421,"answer":20,"analysis":33},896808,"在工程量清单中，最能体现分部分项工程项目自身价值的本质的是（ ）。",[422,423,424,425],{"key":20,"text":339,"correct":26},{"key":24,"text":341,"correct":22},{"key":28,"text":343,"correct":22},{"key":31,"text":345,"correct":22},{"id":427,"libraryId":5,"type":15,"typeLabel":16,"stem":428,"options":429,"answer":24,"analysis":33},896809,"根据《建设工程工程量清单计价规范》（GB50500-2013），关于计日工，下列说法中正确的是（ ）。",[430,432,434,436],{"key":20,"text":431,"correct":22},"计日工表包括各种人工，不应包括材料、施工机械",{"key":24,"text":433,"correct":26},"计日工按综合单价计价，投标时应计入投标总价",{"key":28,"text":435,"correct":22},"计日工表中的项目名称由招标人填写，工程数量由投标人填写",{"key":31,"text":437,"correct":22},"计日工单价由投标人自主确定，并按计日工表中所列数量结算",{"id":439,"libraryId":5,"type":15,"typeLabel":16,"stem":440,"options":441,"answer":24,"analysis":33},896810,"根据《建设工程量清单计价规范》（GB50500-2013），下列关于工程量清单项目编码的说法中，正确的是（ ）。",[442,444,446,448],{"key":20,"text":443,"correct":22},"第三级编码为分部工程顺序码，由三位数字表示",{"key":24,"text":445,"correct":26},"第五级编码应根据拟建工程的工程量清单项目名称设置，不得重码",{"key":28,"text":447,"correct":22},"同一标段含有多个单位工程，不同单位工程中项目特征相同的工程应采用相同编码",{"key":31,"text":449,"correct":22},"补充项目编码以“B”加上计算规范代码后跟三位数字表示，并应从001起顺序编制。",{"id":451,"libraryId":5,"type":15,"typeLabel":16,"stem":452,"options":453,"answer":20,"analysis":33},896811,"关于分部分项工程量清单编制的说法，正确的是（ ）。",[454,456,458,460],{"key":20,"text":455,"correct":26},"施工工程量大于按计算规则计算出的工程量的部分，由投标人在综合单价中考虑",{"key":24,"text":457,"correct":22},"在清单项目“工程内容”中包含的工作内容必须进行项目特征的描述",{"key":28,"text":459,"correct":22},"计价规范中就某一清单项目给出两个及以上计量单位时应选择最方便计算的单位",{"key":31,"text":461,"correct":22},"同一标段的工程量清单中含有多个项目特征相同的单位工程时，可采用相同的项目编码",{"id":463,"libraryId":5,"type":15,"typeLabel":16,"stem":464,"options":465,"answer":24,"analysis":33},896812,"招标人在工程量清单中提供的用于支付必然发生但暂不能确定价格的材料、工程设备的单价及专业工程的金额是（ ）。",[466,468,470,472],{"key":20,"text":467,"correct":22},"暂列金额",{"key":24,"text":469,"correct":26},"暂估价",{"key":28,"text":471,"correct":22},"总承包服务费",{"key":31,"text":473,"correct":22},"价差预备费",{"id":475,"libraryId":5,"type":15,"typeLabel":16,"stem":476,"options":477,"answer":20,"analysis":33},896813,"在分部(分项)工程项目清单中，表示专业工程分类编码的是（ ）。",[478,480,482,484],{"key":20,"text":479,"correct":26},"第一级编码",{"key":24,"text":481,"correct":22},"第二级编码",{"key":28,"text":483,"correct":22},"第三级编码",{"key":31,"text":485,"correct":22},"第四级编码",{"id":487,"libraryId":5,"type":15,"typeLabel":16,"stem":488,"options":489,"answer":24,"analysis":33},896814,"分部(分项)工程量清单项目编码中，第二级表示（ ）。",[490,492,494,496],{"key":20,"text":491,"correct":22},"专业工程代码",{"key":24,"text":493,"correct":26},"附录分类顺序码",{"key":28,"text":495,"correct":22},"分部工程顺序码",{"key":31,"text":497,"correct":22},"分项工程项目名称顺序码",{"id":499,"libraryId":5,"type":15,"typeLabel":16,"stem":500,"options":501,"answer":20,"analysis":33},896815,"投标人经复核认为招标人公布的招标控制价未按照规定进行编制的，应在招标控制价公布后（ ）天向招标投标监督机构或工程造价管理机构投诉。",[502,503,504,506],{"key":20,"text":103,"correct":26},{"key":24,"text":369,"correct":22},{"key":28,"text":505,"correct":22},"15",{"key":31,"text":507,"correct":22},"20",{"id":509,"libraryId":5,"type":15,"typeLabel":16,"stem":510,"options":511,"answer":20,"analysis":33},896816,"编制工程量清单时，招标人自行供应材料、工程设备的，总承包服务费按招标人供应材料、工程设备价值的（ ）计算。",[512,514,516,518],{"key":20,"text":513,"correct":26},"1%",{"key":24,"text":515,"correct":22},"1．5%",{"key":28,"text":517,"correct":22},"3%",{"key":31,"text":519,"correct":22},"5%",{"id":521,"libraryId":5,"type":15,"typeLabel":16,"stem":522,"options":523,"answer":24,"analysis":33},896818,"措施项目中的安全文明施工费按照《建设工程工程量清单计价规范》(GB50500--2013)的要求，应按照（ ）规定的标准计取。",[524,526,527,529],{"key":20,"text":525,"correct":22},"县级以上人民政府建设行政主管部门",{"key":24,"text":283,"correct":26},{"key":28,"text":528,"correct":22},"国务院建设行政主管部门",{"key":31,"text":530,"correct":22},"国务院价格主管部门",{"id":532,"libraryId":5,"type":15,"typeLabel":16,"stem":533,"options":534,"answer":20,"analysis":33},896819,"招标人要求总承包人对专业工程进行统一管理和协调的，总承包人可计取总承包服务费，其取费基数为（ ）。",[535,537,539,541],{"key":20,"text":536,"correct":26},"专业工程估算造价",{"key":24,"text":538,"correct":22},"投标报价总额",{"key":28,"text":540,"correct":22},"分部分项工程费用",{"key":31,"text":542,"correct":22},"分部分项工程费与措施费之和",{"id":544,"libraryId":5,"type":15,"typeLabel":16,"stem":545,"options":546,"answer":28,"analysis":33},896820,"关于招标控制价及其编制的说法，正确的是（ ）。",[547,549,551,553],{"key":20,"text":548,"correct":22},"综合单价中包括应由招标人承担的风险费用",{"key":24,"text":550,"correct":22},"招标人供应的材料，总承包服务费应按材料价值的1.5%计算",{"key":28,"text":552,"correct":26},"措施项目费应按招标文件中提供的措施项目清单确定",{"key":31,"text":554,"correct":22},"招标文件提供暂估价的主要材料，其主材费用应计入其他项目清单费用",{"id":556,"libraryId":5,"type":15,"typeLabel":16,"stem":557,"options":558,"answer":20,"analysis":33},896821,"关于招标控制价的相关规定，下列说法中正确的是（ ）。",[559,561,563,565],{"key":20,"text":560,"correct":26},"国有资金投资的工程建设项目，应编制招标控制价",{"key":24,"text":562,"correct":22},"招标控制价应在招标文件中公布，仅需公布总价",{"key":28,"text":564,"correct":22},"招标控制价超过批准概算3%以内时，招标人不必将其报原概算审批部门审核",{"key":31,"text":566,"correct":22},"当招标控制价复查结论超过原公布的招标控制价3%以内时，应责成招标人改正",{"id":568,"libraryId":5,"type":15,"typeLabel":16,"stem":569,"options":570,"answer":24,"analysis":33},896823,"建设工程施工投标报价程序中，确定基础标价的紧后工作是（ ）。",[571,573,575,577],{"key":20,"text":572,"correct":22},"标书编制",{"key":24,"text":574,"correct":26},"选择报价策略调整标价",{"key":28,"text":576,"correct":22},"招标文件研究",{"key":31,"text":578,"correct":22},"计算投标报价",{"id":580,"libraryId":5,"type":15,"typeLabel":16,"stem":581,"options":582,"answer":20,"analysis":33},896824,"指在不影响工程总报价的前提下，通过调整内部各个项目的报价，以达到既不提高总报价、不影响中标，又能在结算时得到更理想的经济效益的报价方法是（ ）。",[583,585,587,589],{"key":20,"text":584,"correct":26},"不平衡报价法",{"key":24,"text":586,"correct":22},"多方案报价法",{"key":28,"text":588,"correct":22},"突然降价法",{"key":31,"text":590,"correct":22},"无利润报价法",{"id":592,"libraryId":5,"type":15,"typeLabel":16,"stem":593,"options":594,"answer":24,"analysis":33},896825,"投标人在投标前期研究招标文件时，对合同形式进行分析的主要内容为（ ）。",[595,597,599,601],{"key":20,"text":596,"correct":22},"承包商任务",{"key":24,"text":598,"correct":26},"计价方式",{"key":28,"text":600,"correct":22},"付款办法",{"key":31,"text":602,"correct":22},"合同价款调整",{"id":604,"libraryId":5,"type":15,"typeLabel":16,"stem":605,"options":606,"answer":20,"analysis":33},896826,"投标人在投标报价时，应优先被采用为综合单价编制依据的是（ ）。",[607,609,611,613],{"key":20,"text":608,"correct":26},"企业定额",{"key":24,"text":610,"correct":22},"地区定额",{"key":28,"text":612,"correct":22},"行业定额",{"key":31,"text":614,"correct":22},"国家定额",[616,619,622,625,628,631],{"id":15,"name":617,"category":7,"favorite":618},"领导干部任职前廉政法规知识测试题",92,{"id":620,"name":621,"category":7,"favorite":15},595,"建筑结构与设备",{"id":623,"name":624,"category":7,"favorite":15},715,"招标采购专业知识与法律法规",{"id":626,"name":627,"category":7,"favorite":15},848,"市政方向-通用基础",{"id":629,"name":630,"category":7,"favorite":8},534,"BIM工程师",{"id":632,"name":630,"category":7,"favorite":8},535]