[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897720":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897720,581,2,"多选题","根据《政府采购法》，下列项目中，可以采用单一来源采购方式的有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","只能从唯一供应商处采购的项目",true,{"key":16,"text":17,"correct":18},"B","采用公开招标所需时间不能满足用户紧急需要的项目",false,{"key":20,"text":21,"correct":18},"C","采购的货物规格和标准统一，现货货源充足且价格变化幅度小的项目",{"key":23,"text":24,"correct":14},"D","发生了不可预见的紧急情况下不能从其他供应商处采购的",{"key":26,"text":27,"correct":18},"E","技术复杂，事先不能计算出标的价格总额的项目","AD","可以采用单一来源方式进行采购：（1）只能从唯一供应商处采购的；（2）发生了不可预见的紧急情况不能从其他供应商处采购的；（3）必须保证原有采购项目一致性或者服务配套的要求，需要继续从原供应商处添购，且添购资金总额不超过原合同采购金额10％的。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]