[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897717":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897717,581,2,"多选题","在施工过程中， 施工人员发现设计图纸不符合技术标准， 施工单位技术负责人采取的正确做法有（ ）",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","继续按照工程设计图纸施工",false,{"key":16,"text":17,"correct":14},"B","按照技术标准修改工程设计",{"key":19,"text":20,"correct":14},"C","追究设计单位违法责任",{"key":22,"text":23,"correct":24},"D","及时提出意见和建议",true,{"key":26,"text":27,"correct":24},"E","告知建设单位","DE","",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]