[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897687":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897687,581,2,"多选题","承包人根据已办理的竣工结算文件，向发包人提交竣工结算款支付申请。该申请中包括的主要内容有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","A．竣工结算合同价款总额",true,{"key":16,"text":17,"correct":14},"B","B．累计已实际支付的合同价款",{"key":19,"text":20,"correct":21},"C","累计已扣除的各种款项金额",false,{"key":23,"text":24,"correct":14},"D","实际应支付的竣工结算款金额",{"key":26,"text":27,"correct":14},"E","应扣留的质量保证金","ABDE","承包人提交竣工结算款支付申请。包含的内容有竣工结算合同价款总额累计已实际支付的合同价款应扣留的质量保证金实际应支付的竣工结算款金额。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]