[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897686":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897686,581,2,"多选题","某桥梁工程在施工过程中，由于发包人修改桥梁设计，导致承包人暂停施工1 个月，由此承包人可索赔的费用有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","A．窝工费",true,{"key":16,"text":17,"correct":14},"B","B．材料价格上涨费",{"key":19,"text":20,"correct":14},"C","机械台班上涨费",{"key":22,"text":23,"correct":24},"D","利润",false,{"key":26,"text":27,"correct":14},"E","现场管理费","ABCE","由于利润通常是包括在每项实施工程内容的价格之内的，而延长工期并未影响削减某些项目的实施，也未导致利润减少。所以，一般监理工程师很难同意在工程暂停的费用索赔中加进利润损失。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]