[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897683":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897683,581,2,"多选题","工程项目选择合同计价形式时，主要依据的是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","A．设计图纸深度",true,{"key":16,"text":17,"correct":14},"B","B．工期长短",{"key":19,"text":20,"correct":21},"C","工程招标方式",false,{"key":23,"text":24,"correct":14},"D","工程规模",{"key":26,"text":27,"correct":14},"E","工程复杂程度","ABDE","工程项目选择何种计价形式，主要与工程项目本身的特点有关，与采用什么招标方式没有关系。 故选择ABDE。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]